Fixed Price vs Time and Materials: Which Contract to Use?

Fixed price vs time and materials compared: risk, pricing, not-to-exceed caps and how to invoice each contract type, with a worked example for both.

By Invoice Creator Editorial Team 10 min read

Quick answer: In fixed price vs time and materials, a fixed price contract charges one agreed total for a defined scope, so the seller carries overrun risk. A time and materials (T&M) contract bills actual hours at set rates plus materials, so the buyer carries the risk, often limited by a not-to-exceed cap. Choose fixed price for clear scope, T&M for uncertain scope.

The contract type you choose shapes how you quote, how you track work and how you invoice. Get it wrong and you either work for a fraction of your rate or lose the client over a surprise bill. This guide compares fixed price and time and materials contracts side by side, runs the same project through both models with real numbers, and shows how T&M contract invoicing and fixed fee invoicing look in practice. Either way, you can produce the invoices with our free invoice generator.

Fixed price vs time and materials at a glance

FactorFixed priceTime and materials
PriceOne agreed totalHours multiplied by rate, plus materials
Who carries overrun riskSellerBuyer (seller above any cap)
Best when scope isClear, stable, well documentedUncertain, evolving, exploratory
Budget certainty for clientHighLow without a cap
Profit upside for sellerHigher if you work efficientlyCapped at your hourly margin
Admin effortUpfront scoping, change ordersTimesheets, receipts, regular reporting
Typical invoicingMilestones or deposit and balanceWeekly or monthly, hours and costs itemized
Main dispute riskWhat is in or out of scopeWhether hours were necessary

What is a fixed price contract?

A fixed price (or fixed fee, lump sum) contract sets a single price for a defined deliverable. The client knows the total before work starts, and you are paid that total whether the job takes 80 hours or 160. Fixed price works well for repeatable, well-understood work: a five-page brochure website, a bookkeeping catch-up of a known number of months, a standard installation.

The key documents are a detailed scope and a clear change process. A statement of work sets out deliverables, assumptions, exclusions and acceptance criteria. When the client asks for something outside it, you price it separately with a change order rather than absorbing it.

What is a time and materials contract?

A time and materials contract bills the client for actual labor at agreed hourly or daily rates, plus the actual cost of materials and expenses. The US Federal Acquisition Regulation describes it as acquiring supplies or services on the basis of direct labor hours at specified fixed hourly rates (covering wages, overhead, general and administrative costs and profit) and materials at cost, and says it may be used only when it is not possible to estimate accurately the extent or duration of the work. It also requires a ceiling price that the contractor exceeds at its own risk (see FAR 16.601, time-and-materials contracts). Private contracts are not bound by the FAR, but the same logic is a good model for small businesses.

T&M suits discovery work, troubleshooting, renovations where you cannot see behind the walls, ongoing support and any project where the client expects to change direction. For a freelancer with no material costs, T&M is essentially hourly billing; our guide to invoicing for hourly work covers timesheets and rate presentation.

Not-to-exceed caps

A not-to-exceed (NTE) amount turns open-ended T&M into something a client's finance team can approve. You bill actual time and materials up to the cap. If you approach it, you warn the client early and either stop, agree a higher cap, or finish at your own cost. Track the running total on every invoice so nobody is surprised.

Worked example: one project, two contract types

A freelance developer is asked to rebuild a client's website. She estimates 120 hours at her rate of $95 an hour: 120 multiplied by $95 = $11,400 of labor.

  • Fixed price quote: she adds a 15% contingency for risk: $11,400 multiplied by 1.15 = $13,110.
  • T&M quote: $95 an hour for actual hours, plus licences and stock images at cost, with a not-to-exceed cap of $13,000 on labor.

Now look at three possible outcomes for actual labor hours:

Actual hoursT&M labor billT&M bill with $13,000 capFixed priceEffective rate on fixed price
105$9,975$9,975$13,110$124.86/hr
120$11,400$11,400$13,110$109.25/hr
140$13,300$13,000$13,110$93.64/hr

Check the figures: 105 multiplied by $95 = $9,975; 140 multiplied by $95 = $13,300, which the cap reduces to $13,000. On the fixed price, $13,110 divided by 105 = $124.86, divided by 120 = $109.25, and divided by 140 = $93.64 an hour.

The lesson: if she works efficiently, fixed price pays her far more per hour. If the job overruns, fixed price still beats capped T&M slightly here only because the contingency was larger than the cap; at 160 hours the fixed price would fall to about $81.94 an hour ($13,110 divided by 160). For the client, T&M is cheaper unless the project overruns significantly. That trade-off is the whole decision.

How the invoices look

Fixed price, invoiced by milestone (40% / 30% / 30%):

  • Invoice 1, on signing: 40% of $13,110 = $5,244.
  • Invoice 2, design approved: 30% of $13,110 = $3,933.
  • Invoice 3, site launched: 30% of $13,110 = $3,933.
  • Total: $5,244 + $3,933 + $3,933 = $13,110.

Each invoice names the milestone and shows the contract total and amounts previously billed. Our guide to milestone payments covers schedules and wording.

T&M, invoiced monthly. In October she logs 52 hours and buys a plugin licence for $180 and stock images for $240, both billed at cost:

LineQtyRateAmount
Development, October 1 to 31 (timesheet attached)52 hrs$95.00$4,940.00
Plugin licence, at cost1$180.00$180.00
Stock images, at cost1$240.00$240.00
Total$5,360.00

Check: 52 multiplied by $95 = $4,940; $4,940 + $180 + $240 = $5,360. In the notes she adds: "Labor billed to date: $4,940 of $13,000 not-to-exceed; remaining $8,060." ($13,000 minus $4,940 = $8,060.) Materials are listed separately so the client can match them to receipts; see reimbursable expenses on an invoice for how to present pass-through costs. In our invoice generator, each of these is simply a line item with a quantity and rate, and the notes field carries the cap tracking.

Which contract type suits which work?

Type of workUsual fitWhy
Brochure website from a templateFixed priceScope is predictable and repeatable
Bug fixing on an unfamiliar codebaseT&MEffort is unknown until the problem is found
Kitchen renovation with known layoutFixed price with allowancesMost work is defined; allowances cover finishes
Repairs behind walls or floorsT&M with capHidden conditions make estimates unreliable
Monthly bookkeepingFixed monthly feeVolume is stable from month to month
Catch-up bookkeeping for messy recordsT&M or fixed after reviewState of records is unknown until reviewed
Strategy or discovery workshopFixed priceTime-boxed with a defined output
Ongoing support and small changesT&M or retainerRequests vary and arrive over time

The pattern is consistent: the more predictable the work, the more sense a fixed price makes, and the more hidden or changing the work, the safer time and materials becomes for both sides.

How to choose: a 6-step decision process

  1. Rate scope clarity. Can you list every deliverable and acceptance criterion today? If yes, fixed price is viable. If not, lean T&M.
  2. Check your estimating history. If your past estimates for similar work were within 10% to 15% of actuals, you can price fixed fees confidently.
  3. Ask about the client's budget process. Some clients need a fixed number to get approval; offer T&M with a cap if scope is uncertain.
  4. Assess change risk. Many stakeholders, new technology or unclear requirements mean frequent changes, which suit T&M.
  5. Price the risk. If you choose fixed price, add contingency in proportion to uncertainty, and write exclusions.
  6. Consider a hybrid. Paid T&M discovery, then fixed price for the defined build, then T&M support.

T&M contract invoicing best practices

  • Bill on a short cycle. Weekly or monthly invoices keep the client informed and protect your cash flow.
  • Itemize roles and rates. If several people work on the job, list each role's hours separately.
  • Attach timesheets. Clients approve faster when they can see what the hours covered.
  • Separate materials from labor. State whether materials are at cost or include a markup. Our article on the labor and materials invoice shows the standard layout.
  • Show the running total against the cap on every invoice.
  • Number invoices consistently. A simple sequence from an invoice number generator makes it easy for both sides to track a long engagement.

Fixed price invoicing best practices

  • Take a deposit. A first payment on signing reduces risk and confirms commitment.
  • Tie each invoice to an objective milestone that the client can verify, such as "design approved in writing".
  • Show progress: contract total, this invoice, previously billed and remaining balance.
  • Bill change orders separately so the base contract total stays clean.
  • Do not track hours only for the client. Track them for yourself, so you know your real effective rate and can price the next fixed bid better.

Managing the risks of each model

Fixed price risks

  • Underestimating. The single biggest risk. Break the work into tasks of no more than a day or two each, estimate each, and compare with past actuals before adding contingency.
  • Vague acceptance criteria. If "done" is not defined, the client can keep requesting tweaks within the fixed fee. Define the number of revision rounds and what counts as sign-off.
  • Client delays. Waiting for content, approvals or access extends the timeline and ties up your capacity. Include a clause that lets you re-schedule or bill a restart fee if the client causes a long delay.
  • Front-loaded costs. If you buy materials or subcontract early, make sure the first milestone payment covers them.

Time and materials risks

  • Client budget anxiety. Without a cap or regular updates, clients worry about an open-ended bill. Send a short weekly summary of hours used and hours remaining against the estimate.
  • Disputes over efficiency. The client may question whether hours were necessary. Detailed timesheet descriptions ("migrated 42 product pages, fixed image paths") answer that before it is asked.
  • Hitting the cap early. Warn the client when you reach around 75% of the not-to-exceed amount, with a forecast of the remaining work, so they can approve more budget or reduce scope.
  • Lower upside. Your income is limited to hours worked. Review your rate regularly, especially as your speed improves.

Clauses to include in either contract

Whichever model you choose, these terms prevent most billing disputes:

  • Scope and assumptions, or for T&M, the estimated scope the hours are based on.
  • Rates for each role, plus how materials are charged (at cost or cost plus a stated markup).
  • Invoicing schedule: milestones for fixed price, weekly or monthly for T&M.
  • Payment terms such as net 15 or net 30, and any late fee your local law allows.
  • Change process: how new requests are priced and approved in writing.
  • Cap and notification rules for T&M, including when you will warn the client.
  • Termination: what is owed if either side ends the contract early, usually work completed to date plus committed materials.

Putting these in a short contract or statement of work takes an hour and saves far longer arguing over an invoice later.

Beyond fixed price and T&M

Two other models are worth knowing. Cost plus bills actual costs plus a fixed fee or percentage; see our sibling guide to cost plus pricing. Value-based pricing sets the fee by the result's worth to the client rather than by hours or costs; see value-based pricing. Ongoing work is often sold as a monthly retainer, which behaves like a fixed price for a fixed block of time. If you are setting hourly rates for T&M work from scratch, our guide to consulting rates covers how to benchmark them.

Create your project invoice. Whether you bill fixed price milestones or monthly time and materials, our free invoice generator lets you itemize hours, materials and milestones, track amount paid and balance due, and download a professional PDF. For a clean look, try the agency invoice template.

Frequently asked questions

What is the difference between fixed price and time and materials?

A fixed price contract sets one total price for a defined scope, regardless of how many hours the work takes. A time and materials (T&M) contract bills actual hours at agreed hourly rates plus materials at cost or cost plus a markup. With fixed price, the seller carries the risk of overruns. With T&M, the buyer carries it, unless the contract adds a not-to-exceed cap that shifts some risk back to the seller.

Which is better for the client, fixed price or T&M?

Fixed price is better for a client who needs budget certainty and can describe the scope clearly up front. T&M is better when the scope is uncertain or likely to change, because the client only pays for work actually done and does not pay a contingency built into a fixed quote. Many clients prefer T&M with a cap, which gives flexibility with a known worst case.

How do I price a fixed price project?

Estimate hours by task, multiply by your hourly rate, add expected expenses, then add a contingency for risk, often 10% to 25% depending on how well defined the scope is. Check the result against market rates and the value to the client. Write the scope, assumptions and exclusions in detail, because anything outside them should be billed as a change order rather than absorbed into the fixed fee.

What is a not-to-exceed (NTE) clause?

A not-to-exceed clause sets a maximum amount the client will pay under a time and materials contract. You bill actual hours and materials until the cap is reached; anything beyond it is at your own cost unless the client agrees to raise the cap. In US federal contracting, FAR 16.601 requires T&M contracts to include a ceiling price that the contractor exceeds at its own risk.

How do you invoice a time and materials contract?

Invoice on a regular cycle, usually weekly or monthly. List labor as hours multiplied by rate for each role or person, then list materials and expenses separately with receipts or cost references. Show the period covered, the running total against any cap and the remaining budget. Attach or reference timesheets so the client can check hours quickly, which reduces disputes and speeds payment.

How do you invoice a fixed price contract?

Most fixed price projects are invoiced by milestone or percentage of completion, for example 40% on signing, 30% at a midpoint deliverable and 30% on final acceptance. Each invoice should name the milestone, the contract total, the percentage being billed and the amounts previously invoiced. Smaller projects may be invoiced 50% upfront and 50% on delivery, or in full on completion.

Can a contract mix fixed price and time and materials?

Yes, hybrid contracts are common. A typical structure is a fixed price for a well-defined phase, such as discovery or a core build, with T&M for open-ended work like support, integrations or post-launch changes. Some projects start with a T&M discovery phase that produces a detailed scope, and then the build is quoted as fixed price. Keep each part on separate invoice lines so both sides can track them.

What happens if a fixed price project takes longer than expected?

If the overrun comes from your own underestimate, you normally absorb it, which lowers your effective hourly rate. If it comes from the client changing or adding scope, the contract should let you raise a change order with an extra fee or timeline. That is why fixed price contracts need clear scope, acceptance criteria and a change process written in before work starts.

Is time and materials the same as hourly billing?

They are closely related. Hourly billing usually refers to labor only, billed at one or more hourly rates. Time and materials adds the cost of materials, equipment, subcontractors and expenses used on the job, either at cost or with a markup. For a freelancer with no material costs, a T&M contract and an hourly contract look almost identical on the invoice.